Case Studies

Divider image

UBHT Bristol Eye Hospital

Design and Specification | Healthcare

The Challenge

Following a competitive tender process Electrio was awarded the contract to upgrade the existing 3200amps Dual Supply Changeover Panel. This included new Low Voltage supplies being taken from existing High Voltage transformers, as well as replacing the sub main distribution panel that feeds the Eye Hospital.

The Solution

All preparation work for the electrical installation was carried during normal hours, whilst the actual sub main supplies feeding clinical areas were transfered over during evenings and weekends to suit clinical departments. 

During the course of this project our electricians encountered additional challenges because of the various modifications that had been carried out previously, over the years, to the existing switchgear. We also discovered that there were different phase rotations between essential and non-essential supplies, along with several borrowed neutrals between supplies. Despite this, we covercame these difficulties to provide a safe installation.

“Just to say thank you to all those involved in this project - for delivering the job in time, on budget and to an excellent standard. ”

Business Development & Planning Director, Wiltshire Community Health Services

“Thank you for your help in being able to complete on time a very difficult project. This was a lot of work condensed into two weeks and without your help could not have been achieved, please pass our gratitude onto all your operatives who took part.”

Operations Manager, MIDAS property services

“Special thanks for the last push over the weekend to complete all of our tasks. Please pass on our thanks to all of your teams, you have done us proud in the project department. Well done.”

Dairy Crest Limited

accreditation-chas icon
accreditation-dbs icon
accreditation-pasma icon
accreditation-ssip icon
accreditations-niceic icon
accreditations-eca icon
accreditations-safe-contractor icon